New Water Treatment Facilities

 

The new facilities extend the Village's pioneering tradition of excellence. Durable "state-of-the-art" technology is used throughout, adding 1.8 million gallons of treatment capacity for use today with an ultimate designed treatment capacity of 5.4 million gallons per day. The Village continues to invest wisely in the future and honor the commitment of providing world-class service to its' residents. The Village also acknowledged and thanked their engineers (Arcadis RMA). contractors (Wharton-Smith Inc.) and Village staff for bringing this project to completion on time and on budget.

Water Treatment Photo 2 Water Treatment Photo 3 Water Treatment Photo 4

FACTS

  • Total Project Cost = $13,132,000
  • Constructed On Time and On Budget
  • Addition of New Reverse Osmosis Facilities Result in Total Treatment Capacity of 11 Million Gallons Per Day
  • Construction Components
    • New Treatment Building – 150 mph Hurricane Rated
    • New 1.8 Million Gallons Per Day RO Treatment Expandable to 5.4 Million Gallons Per Day
    • New High Service Pumps
    • New Deep Injection Well to Dispose of Concentrate Water in Eco-Friendly Way
    • New Degasifier Units
    • New Emergency Standby Generator & Diesel Storage Facilities.

If you like more information about the Water Treatment Facility processes and technology, please visit the Village’s website Utility Department or call (561) 791-4000.